Skip to main content

No D-wall, No problem!

Ahmedabad Metro (UG-1) Project team launches TBM without Diaphragm Wall for the first time in India. The method was previously used in Istanbul Metro, writes Pratik Kolekar

An innovation can alter the course of things significantly while paving the way for record-breaking milestones. At the Ahmedabad Underground Metro Project (UG-1), Tunnel Boring Machines (TBM) were launched without Diaphragm Wall (D Wall) for the first time, for any Metro project, in India. This alternate methodology helped to speed up construction of Kankaria Metro Station, and, eventually helped to speed up tunnelling for the remaining project.

In the UG-1 project of Ahmedabad Metro, Afcons is constructing two underground stations, twin tunnels of about 3.5km length in total, a cut and cover section, and a ramp connecting elevated and underground sections. The first TBM, ready for commissioning, could not be set in motion as the headwall construction came to a standstill due to delay in handing over of land for Kankaria Station and various other issues. To minimise the delay and speed up execution, the project team adopted a new methodology of TBM passthrough without a D-Wall at Kankaria Station.

In top-down construction methodology the station box D-Wall is placed before TBM passthrough which was not possible at Kankaria Station. This innovative methodology ensured that the delay does not have a domino effect. The station’s width was subsequently increased from 20m to 22m to accommodate the unique TBM manoeuvre.

Underground Tunnel - Ahmedabad Metro
Underground Tunnel between Kankaria and Kalupur stations

Explaining the process, Project Manager S Nakkiran said, “The TBMs were launched from launching shaft as tunnelling started for both east-bound and west-bound routes. The tunnelling for both routes was completed smoothly by constructing permanent rings, and the TBMs were then retrieved at Kalupur Station. As far as Kankaria Station was concerned, the D-Wall of the main station box was constructed in a phased manner once the land was handed over in phases.”

For the first time in India this method was used in a Metro project. Previously, this method was adopted in Istanbul Metro.

To ensure the smooth functioning of TBM, the team also developed an in-house calibration unit for the earth pressure sensor. “Sometimes, the sensors gave a deviated value of earth pressure when the face of the sensor was covered by muck. Hence, its calibration was required. However, getting calibration done from the manufacturer every time, or, renting a unit for it was not cost-effective, and it was time consuming. Therefore, the team developed a calibration unit in-house to address the issue," Nakkiran said.

To expedite work at Kankaria Station, parallel construction was adopted instead of the sequence method. “We could complete the construction of the main station box four months ahead of schedule, and the erection of the Over Track Exhaust (OTE) duct was done five months ahead of schedule. The efforts were also appreciated by the client (Gujarat Metro Rail Corporation),” he added.

Station Concourse Level - Ahmedabad Metro
Station Concourse Level

Ahmedabad Metro (UG-1) Project is slated for inauguration shortly and Afcons has completed the project without compromising on health and safety parameters. The project has clocked twelve-and-half-million Safe Man Hours. The site has earned various accolades, including a four-star rating by the National Safety Council of India, and the Safety Innovation Award from The Institute of Engineers (India) after an extensive evaluation of health and safety management at site. The British Safety Council has also issued an appreciation certificate.

We congratulate the Ahmedabad Metro (UG-1) Project team for this innovation and wish them all the best for the forthcoming project inauguration.

 

Stitch Wall at Kankaria Station
Station
Platform Level
 
 

Afcons fights Covid 19