Afcons has completed 9.6-km Priority Corridor of Kanpur Metro in record time of 22-and-a-half months. Stretching from IIT-Kanpur to Motijheel, the completion of this Corridor marks a major step towards Kanpur’s progressive future.

Here are key facts and figures of this project.

9 elevated stations (handed over for further works):
• IIT Kanpur
• Kalyanpur
• SPM Hospital
• Kanpur University
• Gurudev Chauraha
• Geeta Nagar
• Rawatpur
• Lala Lajpat Rai Hospital
• Motijheel

Casting yard was set up in record time of 60 days.

500 U-Girders were erected in record time of 312 days between Aug 2020 and June 2021.

100 I-Girders were erected in just 186 days.

Out of 9.6kms, 7 kms of viaduct was ready in just 312 days.

5kms stretch (P-01 to P-165) was completed in one stretch.

17 Entry & Exit structures completed.

10mn Safe Man Hours achieved.