Skip to main content

Kanpur Metro

October 2020 has been an extraordinary month for Kanpur Metro team. They achieved several laurels while executing the 9-km stretch from IIT-Kanpur to Motijheel. They include:
• Concreting of 54 U-girders, the highest theoretical limit for casting in 18 beds
• Concreting of 57 T-girders with optimum utilisation of resources
• Erecting 78 T-girders
• Erecting 48 U-girders

As of October 2020, the team has completed:
1,972 piles (90% of the total activity)
303 pile caps (60% of the total activity)
212 U-girders cast
122 U-girders erected
266 piers
1431 (Rm) longitudinal beam
202 T-girders cast
154 T-girders erected
120 pier caps cast
92 pier caps erected

View the project work in progress in Xtreme Engineering story
 

View Pics
 
Inactive

Afcons fights Covid 19