Khapri-MIHAN RoB girders laid in record time of 8 days
[ Source - TheHitavada , Dated - 23 July 2009 ]



AFCONS Pvt.. Ltd. successfullycompleted laving of  girders of railway overbridge  (RoB) of MIHAN in  a record time of just 8 days. Working in co-ordination with officials at Nagpur   Division of Central Railway,  the company successfully  launched 8 girders of 80 tonnes without an incident.


The initial draft plan prepared by project officials with railways estimated girders placing work would require 60-days peiiod wiih bloc of three hours. After launch­ing of iron girder it was matter of time, when the 8 huge girders were plated over the railway line, which is one of the busiest of Indian Railways network, said those familiar with the project. Though the work started during heavy rains, due precautions were tak­en by railway officials and imple­mented in toto, by the company. Eventually, ensured that heavy girders were placed successfully Since getting bloc from railway authorities  during day time was a big problem, the girders were launched during the night time, braving all natural odds.

Vivek Gupta. Sr. Divisional Engineer (Co) Nagpur Division. R K Raj. Executive Engineer (Bridge) and their team were instrumental in ensuring completion of work in record time. The work was executed keeping safety of the officers of MADC and workers on the site informs a press release issued by Deepak Joshi. Public Relation Officer of MADC.

A K Asthana was the Project Manager and S K Jha. Senior Resident Engineer, Consulting Engineering Services India Ltd.. were present throughout the con­struction period at site.

The whole experience of this uphill task which  is one of the fastest launching over Backs for a 6-lane road in India. was well planned and co-ordinat­ed The project was completed due to continuous day and night work Josh,. said "It is indeed a proud moment for entire region, where such dedicated team worked day and night, under tough conditions to fulfill dream of MIHAN.