| Client | : | Mumbai Port Trust, Mumbai,India |
| Consultant |
: | Consulting Engineering Services (India) Pvt. Ltd. |
| Year of Completion | : | 1996 |
| Location | : | Pirpau, Maharashtra, India |

| Project Brief | |
| The work comprised of construction of RCC bored piled approach trestle, 2Kms long including pier head. The approach trestle superstructure was partly precast and partly in-situ for carrying 5.15m. wide roadway, R.C.C. cable ducts and accommodation for 20 pipelines of various diameters. | |