| Client | : | Marine Transport Authority, Ethiopia |
| Consultant |
: | Bertlin & Partners |
| Year of Completion | : | 1989 |
| Location | : | Ethiopia |
| Project Brief | |
| Dredging the existing sea bed to the required level. | |
| Quarrying rubble and forming a bank on the sea bed to the required profile. | |
| Precasting caisson units and placing them over leveled bed of rubble to form piers. | |
| Composite precast and in situ capping beam over caissons | |
| Precast deck unit between the piers and the bank | |
| Electrical, Water supply and fire fighting services. | |
|