Breakwater Shannah
Client : Ministry of Transport & Communication Directorate, Oman (MOTC)
Consultant
: -
Year of Completion : 2008
Location : Shannh, Oman
Breakwater Shannah
Project Brief
Construction of 10.5m wide and 1170m (revised length) long Approach trestle for connecting the berth quay.
Construction of a 258m long new quay structure having 10m wide landing space for berthing of ferry vessels and 60m long ROP patrol boat berth.
Construction of Island Breakwater Using one layer of Armour unit laid in Slope with Coreloc concrete units (1.5 Cum) with width 4.0 Mtr. at Crest at an elevation of +6.0 m CD.